111th St. Streetscape $7.9 million
Investment in Mt. Greenwood Corridor
WEEKLY UPDATE: Monday, August 28, 2023
- The estimated completion will be tentatively in early 2024.
Anticipated construction activities over the next two weeks for the 111th Street Streetscape project. All work will be along the north side of 111th between Homan to Kedzie:
- Remove all sidewalk and curb, & frame and pour 5-foot wide sidewalk along buildings by the end of this week.
- Frame and pour the curb, remove all ADA ramps and start electrical work next week.
The 111th Streetscape project began this past June and is approximately 25% complete. The majority of the construction along the south side of 111th Street between Homan Avenue and Kedzie Avenue is nearing completion and includes new sidewalks, curb and gutter, sewer structures, bus pads, driveways, and alley aprons. By mid-August it is anticipated that the contractor will shift to the north side of 111th Street between Homan Avenue and Kedzie Avenue. A similar progression of work will occur along the north side as was done along the south side. Traffic patterns on 111th Street will remain the same when the construction moves to the north side of the street; however, temporary parking restrictions will be in place on the north side of 111th Street as needed. Tree planting along the new sidewalk will start this fall and continue next spring. All of the existing street lights will be removed and replaced with new light poles in 2024. The project is on schedule to be completed in spring 2024. We encourage all interested business owners and residents to attend the virtual weekly construction meeting with questions or concerns regarding the project – details below.
Microsoft Teams meeting
Join on your computer, mobile app or room device
Click here to join the meeting<https://teams.microsoft.com/l/meetup-join/19%3ameeting_Mjk0ZDBiZWYtYTRjNC00YmVmLWEyZmQtNDgyODAxZjNiOWYz%40thread.v2/0?context=%7b%22Tid%22%3a%2216ed5ab4-2b59-4e40-806d-8a30bdc9cf26%22%2c%22Oid%22%3a%22d4a51250-fa7a-4ced-a8ab-ce36bd052573%22%7d>
Meeting ID: 285 622 710 135
Passcode: BsFaHK
Download Teams<https://www.microsoft.com/en-us/microsoft-teams/download-app> | Join on the web<https://www.microsoft.com/microsoft-teams/join-a-meeting>
Or call in (audio only)
+1 872-810-3297,,547856576#<tel:+18728103297,,547856576#>United States, Chicago
(877) 286-5733,,547856576#<tel:8772865733,,547856576#>United States (Toll-free)
Phone Conference ID: 547 856 576#
Starting May 10th, the Chicago Department of Transportation (CDOT) will break ground on a Streetscape improvement project on 111th Street from Homan Ave. (3400 W) to Sacramento Avenue (3000W). This project will extend the benefits of the previously completed Streetscape project on 111th Street from Central Park to Homan Ave. Through this project, 111th Street will be renovated with infrastructure upgrades and other decorative elements designed to make the area more pedestrian and business-friendly. The project will include:
- New Wider Sidewalks
- New Curb and Gutter
- ADA Ramps
- Upgraded Crosswalks
- Shorter, better-aligned crosswalks
- New Lighting
- Full-Width Roadway Resurfacing
- New Pavement markings and signs
- Site Furnishings
- Trees, Landscaping, and Hanging Baskets
- Sidewalk Medallions (same as those installed in First Section)
- Light Pole Identifiers (same as those installed in First Section)






